Commercial project in Kharadi

Clock Tower

-Built-up area : 2,20,000 Sq.ft.

- Project Scope includes RCC structure, Building external development, Compound wall and road, Waterproofing, Plumbing, External building façade, Electrical work HT/LT installation, Fire Fighting system, DG Set installation, Lift installation. STP plant installation.

- Total Project cost : Approx. 80 Cr.

- Building Floors : Basement + Stilt +15 floor total 17 Floors.

- Floor plate : Big size Floor 950 Sq.m and small floors 780 Sq.m.

Industrial Shed in Ranjangaon MIDC

Carraro India Pvt. Ltd.

- Industrial shed area : 1,00,000 Sq.ft. (one lakh sqft) in different phases

- Scope of project includes complete civil work, PEB Shed, Trimix Flooring, ETP tank, Water tank, Fire Tank etc.

- Total Project cost : Approx. 10 Cr.

Industrial Shed and press machine foundation in Sanaswadi MIDC

Hirschvogel components india pvt. ltd.

- Total Project cost : Approx. 8 Cr.

Agriculture university at Koregaon Bhima.

INDOSWISS Centre of Excellence

- Total Project cost : Approx. 10 Cr.

- Turnkey project for making RCC building.